Reinforcement mesh sheets for a slab by the full sheet grid method. Enter the slab size, pick the sheet size, set the laps from your drawing, and get the sheet count.
Take-off only, not structural design. The mesh type and lap lengths must come from the engineer drawing; this tool never selects them.
Reinforcement mesh calculator
A 10 by 8 m slab with 4.8 by 2.4 m stock sheets and 150 mm laps needs 12 sheets: 3 along the length and 4 across. The calculator above works out the same grid for any slab: sheets each way from the full sheet grid method, times the number of layers, plus your allowance.
How to use
- Enter the slab length and width.
- Pick the sheet size: UK stock 4.8 by 2.4 m, UK merchant 3.6 by 2.0 m, or US welded wire 5 by 10 ft and 6 by 12 ft.
- Enter the end lap and side lap from your engineer drawing. The 150 mm default is one mesh opening, not a specification.
- Pick one or two layers, then read the sheets along, across, and the order total.
Formula
Sheets along = 1 + ceil((span minus sheet) / (sheet minus lap)), the same across the width, times the number of layers. Once the first sheet is placed, every extra sheet contributes its full size minus the lap. The grid is conservative: it does not assume cut offs can be reused elsewhere.
Practical tips
- Use the drawing laps, not the default. Laps are a structural detail. The 150 mm planning default is one mesh opening; your drawing may call for more, especially for heavier meshes.
- Long side along the length. Sheets lay with the long side along the slab length. Turning them the other way changes the count, so the tool fixes the orientation.
- A marked layout can beat the grid. If an off cut from one bay fits another bay with its laps kept, you can order fewer sheets. Every reused piece still needs the specified laps and orientation.
- Order the allowance on top of the grid. The grid already rounds up per row, but cutting around columns and edges still wastes sheets, so keep a small allowance.
Frequently asked questions
How many mesh sheets do I need for a slab?
Work out sheets along and across by the grid method, then multiply by layers. A 10 by 8 m slab with 4.8 by 2.4 m sheets and 150 mm laps needs 12 sheets in one layer.
What size are reinforcement mesh sheets?
UK stock sheets are 4.8 by 2.4 m and merchant sheets are 3.6 by 2.0 m. US welded wire sheets are commonly 5 by 10 ft and 6 by 12 ft.
What lap should mesh sheets have?
Whatever your engineer drawing says. The 150 mm default here is one mesh opening for planning only, never a specification.
Does this calculator pick the mesh type?
No. It counts sheets only. Mesh designation, wire size and lap lengths are structural decisions for the engineer.
More in the concrete calculator hub, including rebar, slabs and footings.