Ready Mix vs Bags Calculator

Compare delivered ready mix against bagged concrete. Enter volume and local prices: see the true cost per yard.



Estimates only. US trucks carry 8 to 10 yd3; UK mixers 6 to 8 m3. Short load fees apply below the supplier minimum. Get local quotes.



Ready mix vs bags: the short answer

Below about 1 cubic yard bags are usually cheaper; above about 2 cubic yards ready mix usually wins on price and always wins on labour. For example: 3 cubic yards at $150 per cubic yard, a $150 delivery fee and $6 per 80 lb bag: ready mix = $450 + $150 = $600 (no short-load fee at 3 yd³ or more); 135 bags = $810; ready mix is $210 cheaper. A second example: 1 cubic yard: ready mix = $150 + $150 + $90 = $390; 45 bags = $270; bags are $120 cheaper. (At 2 yd³ both are $540.) Enter your own local prices in the calculator above for the true cost per yard. Use the currency button to switch between $, £ and €.

How to use the calculator

  1. Enter your concrete volume. Use the unit buttons to switch between cubic yards, cubic metres and cubic feet.
  2. Add a waste margin. Ten percent is a common allowance.
  3. Enter your local prices: ready mix price per cubic yard, delivery fee, short load fee and the minimum load it applies under, and the price per 80 lb bag. All prices are editable, so use figures from local suppliers.
  4. Read the comparison: total cost and cost per cubic yard for each option, plus a verdict showing which is cheaper and by how much.

The formula

Ready mix total = (volume x price per cubic yard) + delivery fee + short load fee, the last only when the volume is under the supplier minimum.

Bags total = ceil(volume x 27 / 0.60) x price per bag. The 27 converts cubic yards to cubic feet, 0.60 is the yield of one 80 lb bag (Quikrete), and ceil rounds up because you cannot buy part of a bag.

Cost per cubic yard = total / volume. The calculator shows both figures so you can compare the true unit cost, not just the headline price.

Practical tips

  • Short-load fees (for example $90) usually apply to orders under about 3 cubic yards. If you are just under the minimum, adding a small second pour can cost less than paying the fee.
  • Below about 1 cubic yard (0.76 m3), bags are usually cheaper; between 1 and 2 cubic yards it depends on delivery and short load fees; above 2 cubic yards, ready mix usually works out cheaper.
  • Labour matters: hand mixing over 100 bags is a full day of hard labour. A ready mix truck arrives mixed and pours straight into the forms.
  • UK part loads: UK barrel mixers carry 6 to 8 cubic metres per trip, so a 2 to 3 cubic metre order is a part load and still far less labour than dozens of bags.
  • Get local quotes: prices vary widely between suppliers, so treat the default prices as editable starting points, not facts.

FAQs

At what volume does ready mix become cheaper than bags?

Below about 1 cubic yard (0.76 m3), bags are usually cheaper; between 1 and 2 cubic yards it depends on delivery and short load fees; above 2 cubic yards, ready mix usually works out cheaper.

What is a short load fee?

Short-load fees (for example $90) usually apply to orders under about 3 cubic yards. It covers the cost of sending a truck that is not full.

How many 80 lb bags make a cubic yard?

Forty five. One 80 lb bag yields 0.60 cubic feet (Quikrete), and a cubic yard holds 27 cubic feet: 27 / 0.60 = 45.

More in the concrete calculator hub, including the cost estimator and the bag calculator. See also the concrete bags vs ready-mix guide.

Price assumptions (examples only): ready-mix $150 per cubic yard, $150 delivery, and a $90 short-load fee on orders under 3 cubic yards; 80 lb bags $6 each. Bags are usually cheaper below about 1 cubic yard (roughly 45 bags of 80 lb). Between 1 and 2 cubic yards it depends on local delivery and short-load fees, so get a quote. Above about 2 cubic yards ready-mix is almost always cheaper and easier.