Ready mix delivery planning. Enter the total volume and truck size: get full loads, the final part load, a load by load breakdown and short load fee warnings.
Estimates only. The delivery fee ($150 per load) and short load fee ($90 for a final load under 3 yd3) are planning assumptions used across this site, and you can edit both. Confirm the actual fees with your supplier before ordering.
Concrete truck load planner
An order of 24.5 cubic yards in 10 yd3 trucks arrives as 3 loads: two full 10 yd3 loads and a final part load of 4.5 yd3, with delivery fees of $450 and no short load fee, because the last load is over 3 yd3. The planner above works out the same split for any order: enter the total volume, pick the truck capacity (8, 9 or 10 yd3), and it lists every load, flags a short load fee when the final truck runs under 3 yd3, and totals the delivery costs.
How to use
- Enter the total concrete volume in cubic yards, cubic metres or cubic feet. Your calculator result usually includes the waste margin already.
- Choose the truck capacity. Ready mix trucks carry 8 to 10 yd3; confirm what your supplier runs.
- Check the load list: full loads first, then the final part load.
- Watch for the short load warning. A final load under 3 yd3 usually attracts a short load fee.
- Adjust the delivery and short load fee fields to your supplier’s rates for a realistic delivery total.
Formula
Full loads = total volume / truck capacity, rounded down. The final load is whatever is left over, and it disappears when the total divides exactly. Delivery fees = number of loads x delivery fee per load, plus the short load fee when the final load is above zero and under 3 yd3.
Not sure how much a truck carries? Read how many cubic yards a concrete truck holds before you plan the order.
Practical tips
- Avoid a tiny final load. An order of 22 yd3 in 10 yd3 trucks ends with a 2 yd3 load and a $90 short load fee. Ordering a little more, or trimming the job to 20 yd3, can cost less overall.
- Exact multiples are cheapest. 20 yd3 in 10 yd3 trucks is two full loads, no part load and no short load fee.
- Small jobs ride in one truck. Anything up to the truck capacity arrives in a single load; a 2.5 yd3 order still pays delivery plus the short load fee, $240 on the planning rates.
- Space the trucks out. Agree arrival gaps with the plant so each load is placed and finished before the next one arrives, especially in hot weather.
- Confirm capacity locally. Legal road limits can cap a big drum below its rated capacity on some routes; ask the supplier what they will actually send.
Frequently asked questions
How many truck loads do I need for 24.5 cubic yards?
Three loads in a 10 yd3 truck: two full loads and a final load of 4.5 yd3. In an 8 yd3 truck it would be four loads, ending with a 0.5 yd3 part load that would attract a short load fee.
What is a short load fee?
A surcharge suppliers add when a truck delivers well below its capacity, because the trip costs them the same to run. On this site’s planning rates it is $90 for a final load under 3 yd3; your supplier’s threshold and fee may differ, so edit the fields to match.
How much concrete fits in one truck?
Standard ready mix trucks carry 8 to 10 cubic yards per load. Enter your volume above and pick the capacity to see the split.
Is it cheaper to order one big load or several small ones?
Fewer, fuller loads cost less: every truck pays a delivery fee, and part loads under 3 yd3 add a short load fee. A single 7 yd3 load in an 8 yd3 truck pays one delivery fee and no short load fee.
More in the concrete calculator hub, including ready mix vs bags, cost and weight.