How Much Concrete for a Fence Post? Bag Counts for 4×4 and 6×6 Posts (US and UK)

Wooden fence post set in a dug hole with concrete being poured around its base on a building site

How Much Concrete for a Fence Post: Worked Bag Counts

Most guides answer this question with a vague range. That is not helpful when you are standing in the builders merchant trying to decide between six bags and ten. This article works the numbers out properly for the two standard jobs: a 4×4 post in a 12 inch hole and a 6×6 post in an 18 inch hole. You get the volume formula shown step by step, plus US and UK bag counts for both jobs.

The short answer: A 4×4 post in a 12 inch hole, 2 ft deep, needs about 1.4 cubic feet of concrete, which is three 80lb bags (or four 25kg bags in the UK). A 6×6 post in an 18 inch hole, 3 ft deep, needs about 4.7 cubic feet, which is eight 80lb bags (or eleven 25kg bags).

The Formula, Step by Step

A post hole is a cylinder with a square post sitting in the middle. The concrete fills the space around the post, so the calculation is simple:

  1. Hole volume = pi x radius squared x depth
  2. Post volume = post width x post width x depth
  3. Concrete volume = hole volume minus post volume

The step most people skip is number 2. The post takes up real space, and forgetting to subtract it is the main reason DIY estimates overshoot. Use 3.1416 for pi, divide by the bag yield, and round UP.

  • 80lb bag = 0.60 cubic feet
  • 60lb bag = 0.45 cubic feet
  • 40lb bag = 0.30 cubic feet
  • 25kg bag = 0.0117 cubic metres
  • 20kg bag = 0.0094 cubic metres

Worked Example 1: 4×4 Post in a 12 Inch Hole, 2 ft Deep

This is the most common fence job. A 4×4 post is actually 3.5 inches square, and the standard hole is 12 inches across and 2 ft deep.

Step 1: hole volume. Radius = 6 inches = 0.5 ft. Volume = 3.1416 x 0.5 x 0.5 x 2 = 1.57 cubic feet.

Step 2: post volume. Cross section = 3.5 x 3.5 = 12.25 square inches = 0.0851 square feet. Volume = 0.0851 x 2 = 0.17 cubic feet.

Step 3: concrete volume. 1.57 minus 0.17 = 1.40 cubic feet.

Step 4: bags (US). 80lb: 1.40 / 0.60 = 2.33, so buy 3. 60lb: 1.40 / 0.45 = 3.11, so buy 4. 40lb: 1.40 / 0.30 = 4.67, so buy 5.

UK metric version: 300 mm hole, 600 mm deep, 100 x 100 mm post. Hole = 3.1416 x 0.15 x 0.15 x 0.6 = 0.0424 cubic metres. Post = 0.1 x 0.1 x 0.6 = 0.006 cubic metres. Concrete = 0.0364 cubic metres. 25kg: 0.0364 / 0.0117 = 3.11, so buy 4. 20kg: 0.0364 / 0.0094 = 3.87, so buy 4.

Worked Example 2: 6×6 Post in an 18 Inch Hole, 3 ft Deep

A 6×6 post is actually 5.5 inches square, and a heavier post wants an 18 inch hole dug 3 ft deep for stability.

Step 1: hole volume. Radius = 9 inches = 0.75 ft. Volume = 3.1416 x 0.75 x 0.75 x 3 = 5.30 cubic feet.

Step 2: post volume. Cross section = 5.5 x 5.5 = 30.25 square inches = 0.2101 square feet. Volume = 0.2101 x 3 = 0.63 cubic feet.

Step 3: concrete volume. 5.30 minus 0.63 = 4.67 cubic feet.

Step 4: bags (US). 80lb: 4.67 / 0.60 = 7.78, so buy 8. 60lb: 4.67 / 0.45 = 10.38, so buy 11. 40lb: 4.67 / 0.30 = 15.57, so buy 16.

UK metric version: 450 mm hole, 900 mm deep, 150 x 150 mm post. Hole = 3.1416 x 0.225 x 0.225 x 0.9 = 0.1431 cubic metres. Post = 0.15 x 0.15 x 0.9 = 0.0203 cubic metres. Concrete = 0.1229 cubic metres. 25kg: 0.1229 / 0.0117 = 10.50, so buy 11. 20kg: 0.1229 / 0.0094 = 13.07, so buy 14.

For your own hole size, try our post hole concrete calculator, which does the cylinder maths for you.

Quick Reference Table

Standard combinations with bag counts already rounded up. The UK figures differ slightly because UK timber sizes are metric.

Post Hole diameter Hole depth Concrete volume 80lb bags 60lb bags 25kg bags 20kg bags
4×4 (100 mm) 10 in (250 mm) 24 in (600 mm) 0.92 ft3 2 3 3 3
4×4 (100 mm) 12 in (300 mm) 24 in (600 mm) 1.40 ft3 3 4 4 4
4×4 (100 mm) 12 in (300 mm) 30 in (750 mm) 1.75 ft3 3 4 4 5
6×6 (150 mm) 16 in (400 mm) 36 in (900 mm) 3.56 ft3 6 8 8 10
6×6 (150 mm) 18 in (450 mm) 36 in (900 mm) 4.67 ft3 8 11 11 14

How Deep Should the Hole Be

The old rule of thumb still holds: bury at least one third of the post’s total length, and never less than 600 mm (2 ft) for a standard fence post. A 6 ft fence post wants 2 ft in the ground. Gate posts and corner posts, which take more load, should go deeper, 900 mm or more.

In cold parts of the US, dig below the local frost line as well, or frost heave will push the post up over winter. Bell the bottom of the hole slightly wider than the top to resist uplift.

Common Mistakes That Waste Bags

  • Forgetting to subtract the post. A 6×6 post in a 3 ft hole displaces 0.63 cubic feet, which is a whole 80lb bag.
  • Buying the exact count. Augered holes are never perfect cylinders. Buy one spare bag per few posts.
  • Mixing too wet. Soup mix is easy to pour but weak when set. Follow the water guidance on the bag.
  • Skipping the gravel base. 100 to 150 mm of compacted gravel under the post helps drainage and stops the post end sitting in water.

Buying for a whole fence run? Add up the per post figure and use our concrete bag calculator to convert the total into bags in one go.

Frequently Asked Questions

How many 80lb bags of concrete do I need for one 4×4 fence post?

Three 80lb bags for a 4×4 post in a 12 inch hole dug 2 ft deep. That covers 1.40 cubic feet of concrete with the post volume subtracted.

How much concrete does a 6×6 post need?

Eight 80lb bags for a 6×6 post in an 18 inch hole dug 3 ft deep. The concrete volume is 4.67 cubic feet after subtracting the post.

How many 20kg bags of concrete per fence post in the UK?

Four 20kg bags for a standard 100 x 100 mm post in a 300 mm hole dug 600 mm deep. For a 150 x 150 mm post in a 450 mm hole dug 900 mm deep, you need fourteen 20kg bags.

Can I use dry mix straight in the hole?

Yes, this is standard practice for fence posts. Set the post, pour dry mix around it, add water, and rod it down to remove air pockets.

Should I put gravel under a fence post?

Yes. A 100 to 150 mm layer of compacted gravel improves drainage and keeps the post end out of standing water.

How long before I can hang a fence panel on a concreted post?

Wait 24 to 48 hours in normal weather before loading the post. In cold weather, wait longer and protect the concrete from frost.

Setting methods compared

Method Hold Drainage Best for
Full concrete to the surface Strongest Poor unless a gravel base is added Tall fences and gates.
Gravel base plus concrete Strong Good Most garden fences; the recommended method.
Dry mix tipped into the hole Moderate Poor Small posts in a hurry; weaker than wet mix.
No concrete, driven or backfilled soil Weak Good Temporary fencing only.

Conclusion

Fence post concrete is simple maths: cylinder volume minus post volume, divided by the bag yield, rounded up. A 4×4 post in a standard hole takes three 80lb bags or four 25kg bags. A 6×6 post in a bigger hole takes eight 80lb bags or eleven 25kg bags. Work it out before you go to the merchant, buy one bag spare, and you will never run short mid pour.

Sources

About the author

Kaleemullah Formulas use standard geometry and published bag yields; sources are linked in each article.